National Grid plc (NYSE:NGG) Q2 2025 Earnings Call Transcript November 7, 2024
Angela Broad : Good morning, and welcome to National Grid’s Half Year Results Presentation. I’m Angela Broad, Head of Investor Relations, and it’s great to have so many of you on the call today. Firstly, please kindly of draw your attention to the cautionary statement at the front of the pack. As usual, the Q&A with John and Andy will follow the presentation. [Operator Instructions] All of today’s materials are available on our website. And of course for any further queries after the call, please reach out to me or one of the IR team. So with that, I’d now like to hand you over to our CEO, John Pettigrew. John?
John Pettigrew: Many thanks, Angela, and good morning, everyone. Thank you for joining us today. As ever I’m here with Andy Agg. And once we’ve been through our respective presentations, we’ll of course be very happy to answer your questions. As you know, in May, we updated our strategy, and announced the actions we’d be taking to make National Grid the preeminent pure play networks business. This marked the beginning of an exciting new area of growth with unmatched visibility on around £60 billion of capital investment in our networks over the next five years and clarity on financing well beyond that. Over the last six months, the pace of change in our industry has continued as has the exciting momentum within National Grid.
We successfully completed the £7 billion rights issue positioning our balance sheet to deliver this growth at pace. We’re delivering on our major capital projects increasing investment to a record £4.6 billion in the first half. In the U.K. construction is already underway on five of our ASTI projects. And in the U.S. regulated CapEx increased 20% year-on-year as we’ve continued our $4 billion upstate upgrade program. And our policy agendas continue to move forward as well. We’re encouraged by the start the new U.K. government has made against their energy priorities. As you would have seen the National Energy System Operator, or NESO was established on the first of October following our sale of the Electricity System Operator to £613 million.
They’ve also formed mission control to help accelerate progress on energy projects needed for 2030. And at the end of this year they will settle their action plan to achieve this taking into account the advice set out this week by the NESO. The NESO’s report is a welcome milestone towards clarity on the steps needed to deliver against this goal and we’ll continue to play our part alongside the government regulator and industry. The government has also commissioned NESO to develop a strategic spatial energy plan setting out where energy assets need to be built and when to meet the country’s 2015 net zero goals. We’re pleased that the King’s speech in July include the expected legislation to reform the planning system. This will help to accelerate the delivery of critical infrastructure something that we’ve long been advocating for.
In the U.S. Massachusetts and New York policymakers are continuing to progress plans to align economic growth and system reliability needs with their clean energy and climate goals. Both states recognize the need for long-term holistic energy planning and we’re encouraged that this is now underway. From a regulatory perspective, we’ve agreed new rates for our downstate New York gas business and for our Massachusetts electric business giving us even greater visibility on our investment plans. And in the U.K. Ofgem’s publication of the sector-specific methodology decision mark the next step in the RIIO-T3 regulatory process. We’ve also achieved another important strategic milestone by completing in September the sale of our final 20% stake in our U.K. gas transmission business for £686 million.
Q&A Session
Follow National Grid Plc (NYSE:NGG)
Follow National Grid Plc (NYSE:NGG)
So as I say, exciting momentum and progress in the last six months that underpins our compelling investor proposition of delivering low-risk high-quality asset growth, strong earnings growth and an inflation protected dividend. Now turning to our financial performance for the first six months. On an underlying basis that is excluding the impact of timing and exceptional items, operating profit from continuing operations was £2 billion, 15% higher compared to the prior year at constant currency. This reflects good performance across all of our regulated businesses, which drove an increase in underlying earnings per share of 8% to 28.1p. Our business delivered a record £4.6 billion of investment, up 19% year-on-year at constant currency. And in line with our policy the Board has declared an interim dividend of 15.84p per share.
Turning next to reliability and safety. Reliability remains strong across our U.K. and U.S. networks despite severe weather in most jurisdictions. Our teams restored outages rapidly and well within regulatory requirements, including in our New York region where during the most significant storms the average time to restore 95% of customers was just 12 hours. As we look ahead, NESO recently published its winter outlook report for the UK in which they’re forecasting an electricity capacity margin of 8.8%, slightly higher than last year’s and broadly in line with recent winters. Overall, we are confident in delivering our usual high standard reliability across our networks in the months ahead, and remain vigilant as we move through the winter in both the UK and the US.
Safety as always remains a critical focus across the business. In the first six months, our Lost Time Injury Frequency rate Was 0.1 in line with our group target. With our significant increase in capital delivery, we are recruiting new contractors working for National Grid for the first time and so we’ve reinforced our protocols to ensure that our high safety standards are maintained. Now moving to our operating performance across the group starting with the UK electricity distribution. Capital investment increased by 6% to £647 million driven by increased customer connections asset health workload and network reinforcements. We’ve also made further progress to improve our customer service including in May when we launched ClearView Connect.
This online tool provides visibility of grid supply point capacity, including a view of the generation connections pipeline to help prospective developers identify the quickest and cheapest connection points. And we’ve made good progress in reforming the connections process. By playing a leading role in the industry’s technical limits initiative, we’ve been able to accelerate the connection offer date on over 280 megawatts of distribution generation. And as mentioned, at our Connections investor event in January, by reviewing projects that aren’t progressing, we’ve been able to remove 3.7 gigawatts of capacity from the contracted connections queue. Looking ahead, whilst we’re still more than three years remaining in ED2, we’re already thinking about the next regulatory cycle.
Yesterday, Ofgem issued its framework consultation which includes wide-ranging questions to help shape the ED3 price control and will respond early in the new year. Turning to UK Electricity Transmission where CapEx increased by 43% to £1.3 billion driven by an increase in customer connections with 2.3 gigawatts of new customer connections in the first half. And good progress on our £1 billion London Power Tunnels project where we successfully energized a 2.5-kilometer circuit between Hurst substation and Crayford. Looking further ahead we’re seeing an increase in transmission scale connection requests for data centers that is driving significant investment for new and upgraded substations in the Southeast. On regulatory developments, Ofgem published in July their decision on the sector-specific methodology, marking the next step in the RIIO-T3 regulatory process that will run through to the final determination at the end of 2025.
We are pleased to see that the document included our commitment to streamlining the overall framework to enable faster decision making on which projects proceed. Proposals for an advanced procurement mechanism, which enables us to secure supply chain capacity early and the introduction of mechanism similar to the ASTI approach to low funding on projects earlier than historically has been the case. As you’d expect we’re engaging constructively with Ofgem as well as wider stakeholders to agree the right regulatory frameworks that delivers a net zero energy system and a fair return. Whilst we are encouraged by Ofgem’s inclusion of a cost of equity range of 4.6% to 6.4% the allowed return needs to be at the top end of the range in order to continue to attract sufficient capital to the sector.
Ofgem also concluded on its inflation consultation with the introduction of a nominal return on fixed rate debt, which will add better matching of allowances to actual debt costs and faster recovery of cash. On the policy front, we’ve seen progress on connections reform and I’m pleased that we now have consensus with government of Ofgem and NESO on the steps that need to be taken. In the second half of 2025 NESO is expected to implement reforms where projects must move through a two-stage process based on a combination of project readiness and alignment with the Clean Power Plan. Turning next to our strategic infrastructure business created last year to deliver the 17 ASTI projects. We’re managing these projects in distinct waves. Wave one comprises the six most advanced projects and Wave two comprises the remaining land which are at earlier stages of development.
We’re well progressed with obtaining the required consents for the first wave of projects and we expect to have all the key equipment and material contracts in place by early next year. As I mentioned earlier, construction has started on five of the first wave including the offshore EGL Eastern Green Links 1 and 2, Yorkshire Green, North London Reinforcement and Bramford to Twinstead. With construction due to start shortly on the Grain to Tilbury project at the end of this fiscal year, we’ll have broken ground in all six well Wave 1 projects. Turning to our Wave 2 projects, we had a number of public consultations running over the summer. And with further consultations planned in 2025, we’re progressing well through the consenting process. We’re making good progress on procurement and are well advanced in securing the supply chain and we’re submitting early construction funding request to Ofgem on Eastern Green Links 3 and 4 in our sealing project to allow these projects to move forward at pace.
Coming to the US and starting with New York. CapEx has continued to be strong increasing 29% to £1.6 billion in the first half. This reflects strong progress with our $4 billion upstate upgrade including our Smart Path Connect project which has reached the halfway point in construction well ahead of schedule. And the work approved under the Climate Leadership and Communities Protection Act, where construction on Phase 1 of the project is progressing well and we’ve just issued the procurement tenders for Phase 2. We’ve also increased investment in our gas network, replacing a further 161 miles of leak-prone pipe, as we continue to reduce our methane emissions. On the regulatory front in August our three-year rate case settlement for our KEDNY and KEDLI gas distribution businesses was approved by the commission.
We expect to invest $5 billion over the next three years with an improved ROE of 9.35%. And we filed for new rates in our Niagara Mohawk business in Upstate New York. The filing proposes transmission investment to integrate renewables, line and substation upgrades and further investment in our leak-prone pipe replacement program. At the end of September as usual the PSC staff provided a rebuttal testimony including a 9.5% cost of equity against our current allowed return of 9% and smaller increases to our allowed – our proposed capital investment. The filing will now continue to progress as we enter settlement negotiations and we’re confident we can reach a constructive outcome by the spring. Turning to policy. We’re in July, a draft report from the New York PSC acknowledged for the first time that New York State is likely to miss its target of 70% renewable generation by 2030.
In response to the report Governor Hochul administration has taken several actions including reconvening the state energy planning Board to draft road map for the state to build a clean energy system for New York taking into account resource adequacy and affordability. As a result a more pragmatic dialogue has opened up. And as you’d expect, we’re engaged in supporting the process, which provides an opportunity to shape a more balanced approach to the energy transition. In New England capital investment increased by 7% to £814 million. This largely reflects the continued steady growth delivered through investment in grid modernization and asset health work and leak-prone pipe replacement activity. From a regulatory perspective, in September the DPU issued its rate case order for Massachusetts Electric business, approving a five-year plan with a revenue increase of around $100 million.
The order includes a new regulatory recovery mechanism that provides timely funding for growing capital investment and updated performance-based rate mechanism providing inflation protection for operating and maintenance costs and increased allowances to cover the increase in cost of storms. Taken together, these enhanced recovery mechanisms will enable us to earn closer to a low return of 9.35%. The DPU has also approved our electric sector modernization plan as a strategic road map to support decarbonization investments. As part of this we filed for $2 billion of investment including upgraded power lines, transformers, substations and technology platforms over the next five years. We expect to propose costs and recovery mechanisms will be agreed ahead of the program starting next summer.
And over the past summer Governor Healey’s administration has been working to pass comprehensive energy and climate legislation. The proposed bill addresses critical issues we’ve been advocating for including setting out an accelerated time line for siting and permitting of clean energy infrastructure projects and we’re hopeful it will progress before the end of the year. And finally in National Grid Ventures, capital investment was 11% lower at £279 million following completion of the Viking Link to Denmark last year partially offset by increased investment in National Renewables and the Isle of Grain. We’ve made good progress on the Propel transmission project through our New York Transco joint venture which will help to deliver offshore wind power from Long Island to the Bronx n New York City and Westchester County.
We’ve made further progress in the fourth phase of the expansion of our Isle of Grain LNG facility which remains on track for completion next summer. And we’ve also commenced the sale process for National Grid Renewables. So as I said at the start we’ve achieved significant progress across all areas of the business in the first half as we continue to support and invest in the energy transition. Let me stop there and hand over to Andy to walk through the numbers before I come back to talk about priorities for the second half. Andy?
Andy Agg: Thank you, John and good morning, everyone. I’d like to highlight that as usual we’re presenting our underlying results excluding timing UK deferred tax and exceptional items and that all results are provided at constant exchange rates unless specified. Our final 20% stake in National Gas is reported as a discontinued operation up until 26th of September when it was sold. As such all earnings from this business have been excluded from the underlying earnings of the continuing group. So starting with our overall performance in the first half. We’ve delivered strong results with underlying operating profit on a continuing basis at £2 billion a 15% increase on the prior year, primarily driven by higher revenues across our UK and US regulated businesses and the non-repeat of a prior year environmental charge in our New York business partially offset by a lower profit in National Grid Ventures.
Underlying earnings per share of 28.1p was 8% higher than the prior year restated figure. This reflects the improved performance from across our regulated businesses and a slight decline in finance costs which more than offset the increased share count following the rights issue. As John said we’ve made excellent progress with our capital program with investment from continuing operations at £4.6 billion another record level and up 19% year-over-year. This has been driven by more connections in our electricity transmission business, accelerated delivery of our ASTI projects, increased pipe replacement across our US gas businesses and a step-up in our Smart Path Connect and CLCPA transmission projects in upstate New York. In line with our policy, the Board has declared an interim dividend of 15.84p per share representing 35% of last year’s rebased full year dividend.
Turning now to our business segments starting with UK electricity distribution. Underlying operating profit was £573 million up £10 million versus the prior year. Increased revenues were partially offset by higher controllable costs which were £21 million higher as we prioritized activities to strengthen the business for the remainder of RIIO-ED2. This included spend on field customer and asset management teams and cost to implement new distribution system operator functionality. We expect the full year controllable cost performance to be broadly in line with the prior year. We’re also on track to deliver our target of £100 million of synergy benefits by FY 2026 having delivered £58 million to-date through leveraging our increased buying power, working more efficiently at the 48 joints transmission and distribution sites across the UK and delivering savings from combining support functions.
Capital investment was £647 million for the half year, an increase of £39 million compared to the prior period primarily driven by higher spend on reinforcement work and asset replacement. In our UK electricity transmission business, Underlying operating profit was £724 million up £68 million compared with the prior period. A strong first half performance was driven by higher allowed revenues and lower controllable costs as we deliver further cost efficiencies. Capital investment was £1.3 billion, 43% higher than the prior period. This reflects work on our RIIO-T2 projects including customer connections as well as the step-up in investments our ASTI projects notably Eastern Green Link 1, Yorkshire Green and our North London reinforcement projects.
Finally in the UK, the electricity system operator delivered an underlying operating profit of £115 million. Moving now to the US, where underlying operating profit for New York was £288 million, £173 million higher than the prior year reflecting higher net revenue driven by an increase in rates and a non-repeat of environmental charge in the prior period. This was partially offset by an increase in depreciation, reflecting the new rate case in our downstate gas businesses KEDNY and KEDLI. Capital investment was GBP 1.6 billion. This was GBP 352 million higher than the prior year helped by a further step-up in investments in the Smart Path Connect and CLCPA transmission projects in Upstate New York and increased investments in our gas distribution networks, reflecting the additional workload approved in our downstate gas rate case.
In New England, underlying operating profit was GBP 237 million GBP 26 million higher than the prior period. This reflects higher rates in our Massachusetts electric and gas businesses driven by the annual performance-based rate mechanism and higher rates from the capital tracker in the gas business, partly offset by higher depreciation and controllable costs. Capital investment was GBP 814 million, GBP 50 million higher than the prior year. This was driven by increased asset condition work in our electricity distribution business and higher gas spend, including leak-prone pipe replacement. Moving to National Grid Ventures, where the underlying contribution was GBP 207 million, including joint ventures. The decrease of GBP 70 million compared to the prior year was, primarily due to the one-off post construction review adjustment on the North Sea Link interconnector in the prior period and lower profitability across the US Ventures businesses.
Capital investments across National Grid Ventures was GBP 279 million, GBP 33 million lower than the prior period, largely reflecting the completion of the Viking interconnector, and partially offset by higher investment at our Grain LNG facility, as we move closer to completing the fourth phase of capacity expansion. Following the announced intention to sell Grain LNG and National Grid Renewables, these assets will be treated as held for sale for accounting purposes from the 30th of September. Our other activities reported an operating loss of GBP 38 million, GBP 25 million higher than the prior period. This was principally driven by changes in the value of National Grid Partners’ investments, which are held at fair value partially offset by a greater number of property sales in the first half compared with the prior period.
Turning to financing costs and tax. Net finance costs were GBP 670 million, down 4% compared to the prior year. The benefits of lower average net debt following the rights issue and lower inflation on index-linked debt were partially offset by the impact of higher refinancing costs, where we have issued GBP 1.8 billion over the first half. The underlying effective tax rate before joint ventures was 11.9% 180 basis points higher than the prior year, principally due to a change in profit mix reflecting the one-off charges impacting the U.S. business last year. Underlying earnings were GBP 1.27 billion with EPS at 28.1p. On cash flow. Cash generated from continuing operations was GBP 2.7 billion down 12% compared to the prior year. This decrease is driven by timing as we returned to prior year balancing charge over recoveries in the system operator.
Excluding timing cash flow from operations is GBP 570 million higher due to improved cash generation across the U.K. and U.S. regulated businesses. In total net debt decreased by GBP 5.1 billion to GBP 38.5 billion compared to the prior year-end reflecting a net cash inflow from continuing operations of GBP 3.5 billion, including the receipt of the rights issue proceeds. Beneficial movements in exchange rates and other non-cash movements of GBP 1.4 billion, and receipt of GBP 686 million from the final 20% sale of National Gas. For the full year, we expect net debt to decrease by around GBP 1.5 billion from the March level, assuming a USD 1.3 exchange rate. In terms of forward guidance, we’ve included detailed guidance for the full year in our results statement as usual.
Relative to our guidance in May, we expect a slightly stronger operating profit for the full year, reflecting the high ESO contribution prior to sale and higher net revenues in our New York business, partially offset by a weaker US dollar outlook. Therefore, we continue to expect strong operational performance and year-on-year operating profit growth of around 10%, as well as reduced financing costs due to lower average net debt. We anticipate this improved performance to be largely offset by the additional share count. Before I hand back to John, I wanted to return to the five-year framework we set out in May, where we anticipated investment of around £60 billion will drive group asset growth of around 10% per annum over the next five years, and a strong underlying EPS CAGR of 6% to 8% from an FY 2025 baseline.
Our framework is underpinned by a supportive regulatory and policy environment, and increasing level of certainty over our multiyear investment program, and a track record of delivery both operationally and financially. Alongside this, we set out a comprehensive financing plan, which supports our investment program and allows us to maintain our strong investment-grade credit rating. And looking ahead, with an expected asset base of around £100 billion by FY 2029 funding clarity, strong earnings growth and an inflation-protected dividend, we’ve further enhanced what I believe is a compelling investor proposition, delivering value creation through both higher asset growth and an attractive dividend yield. With that, I’ll hand you back to John.
John Pettigrew: Many thanks, Andy. Before we move to Q&A, I want to spend the final few minutes setting out our priorities for the remainder of this year, as we continue to focus on efficiently delivering our investment program. Starting with the US, where nearly half of the £60 billion investment will be spent between now and 2029. Following the result of the US presidential election earlier this week, National Grid is looking forward to working with the new administration. As a reminder, the vast majority of our investment is determined at the state level, so we’ll also continue to focus on working closely with state regulators and policymakers, to deliver the infrastructure needed in both our gas and electricity businesses.
From a regulatory perspective, we have three key priorities for the remainder of this year. Firstly, having now filed the new rates in our Niagara Mohawk business, and received the [indiscernible] in September, our aim is to reach a settlement next spring. Secondly, with the new rate plan and enhanced recovery mechanisms in place for our Massachusetts Electric business. Our priority is now to work to earn closer to the [indiscernible] return. And thirdly, we’re focused on agreeing the costs and recovery mechanisms for our recently approved electricity sector modernization plan in Massachusetts. Turning to policy. As mentioned earlier, in New York, the governor is developing a new state energy plan, which we expect will supplement the CLCPA scoping plan and address important issues such as resource adequacy and affordability.
We’re working closely with our stakeholders to ensure it’s a comprehensive road map, to a clean resilient and affordable feature for our customers. Alongside this, the New York PSC is now working to identify urgent and long-term infrastructure projects to support transportation and building electrification, ahead of deploying integrated gas and electricity planning processes. We’ve advocated for this proactive approach and we expect to file our response, identifying the near-term infrastructure needs at the end of the month. And finally, Massachusetts will file our Climate Compliance Plan next spring. This will set out the investments required in our Massachusetts gas network over the next five years and beyond to align to state decarbonization goals, whilst maintaining safe reliable and cost-effective service for our customers.
Moving to the UK, where our priorities are squarely focused on delivery of our suite of major projects. As mentioned earlier, we expect to have construction underway on the first wave of ASTI projects by the end of this year. Our priority for the second wave is to finalize supply chain contracts. We’re already well progressed on this and I’m confident that by early next year, we’ll have secured the Tier 1 supply chain contracts for all 17 of the ASTI projects. This includes awarding the HVDC and converter station contracts raised in Green Links 3 and 4 and Sea Link. We also expect to finalize our £59 billion HVDC framework, which will ensure we have a route to market for procuring materials for offshore projects in the 2030s and beyond. Outside of the ASTI portfolio, we continue to make good progress on the Hinkley connection.
We expect the majority works will be completed by the middle of next year. And on our London Power Tunnels project we’ll commission the Littlebrook to Crayford section over the winter. And finally, we’re on track to connect a total of 4.5 gigawatts of clean energy this year including the Sofia Offshore Wind Farm and the Green Link interconnector. On the regulatory front, a key priority will be the development of our RIIO-T3 business plan, which we’ll submit in December. Our totex submission will comprise two elements: a baseline where we have a high degree of cost certainty, including the first wave of our ASTI projects; and a more extensive pipeline covering the second wave of ASTI projects, as well as further projects aligned to the holistic net-zero pathway in the NESO’s future energy scenarios.
In submitting this plan, we expect the outputs of the government’s Clean Power Plan and changes driven by connection reform to impact our totex submission to a degree. However we don’t anticipate significant change to our £23 billion of expected investment in electricity transmission to 2029 given the high degree of clarity we have over the first few years in RIIO-T3. The second priority will be to continue to engage with Ofgem to ensure they recognize the intense level of international competition for capital by putting forward evidence to support the requirement for an attractive financial framework, including returns being at the high end of Ofgem’s range, appropriate cash characteristics and further opportunities for incentives that will drive value for consumers and National Grid.
When it comes to policy our priority is to continue to work closely with DESNZ and the newly created mission control as they develop their plan for clean power by 2030 and beyond. We’ll continue to advocate for prioritizing a fast track consenting route for electricity transmission projects as part of a broader set of reforms to the planning regime, bringing forward with urgency a community benefits framework for electricity transmission and developing a clean energy skills pipeline including reforms to sequential funding. So in summary, a new and exciting era of growth is firmly underway at National Grid. Having set out our strategy for the next five years, we’ve started to deliver on a £60 billion network investment on both sides of the Atlantic.
Major capital projects in the UK and US are well underway and the business is organized and focused to sustain this progress going forward. This momentum combined with the unparalleled visibility on our investment plans underpin our investment proposition of low-risk high-quality asset growth, strong earnings growth and an inflation protected dividend. This is a huge and exciting time for our industry that will create — which will continue to create significant opportunities for National Grid today and for many decades to come, a bedrock from which we will deliver long-term value and returns for our shareholders. So let me stop there and give you the opportunity to ask me and Andy any questions.
A – John Pettigrew: Okay. So just looking at who we got questions from. So we start with Pavan from JPMorgan.
Pavan Mahbubani: Hi, everyone. Good morning. Thank you for taking my question. I’ve got two please. Firstly, can you remind us when you will be submitting your business plan for the RIIO-ED3 period? And is there any early flavor you can give on what we should be expecting especially when it comes to the mix of CapEx, how you’re thinking about baseline versus uncertainty and how that ties into your five-year frame? And then my second question is on any comment you have on the outcome of US elections? And do you expect this to change your plans for US investment to 2029? Thank you.
John Pettigrew: Yes. Thanks Pavan. Well, in terms of the business plan, the timetable is we do submit the business plan in December this year at the end of December then we’d expect to get a draft determination from Ofgem in the summer probably June next year and then final determination in December 2025. In terms of the flavor, as I said in my speech, effectively the plan is separated into two halves. The first half is a baseline, which includes all the projects that we’ve got confidence that are going to be moving forward or full confidence they’re going to be moving forward and also certainty on cost so things like the ASTI Wave 1 projects. The second bit will be a pipeline that will include all the projects that are aligned with the NESO’s future energy scenarios and we’re doing that because that’s the request from Ofgem in terms of how they want to see the business plan submitted.
As I said in my speech, I think different to previous business plans we’ve had at this stage, because some of the CapEx will be impacted by the connections reform in terms of the location of substations for example and also by where the government gets with the Clean Power Plan following the advice from NESO this week. Some of that pipeline will vary. We don’t think it will impact on the £23 billion that we set out as part of the £60 billion that takes the CapEx to 2029. But we will see some change in that in the early months of next year as we see the outcome of the connections reform. So it’s slightly different than what we’ve seen typically, but at the high level it’s split into two levels a baseline and then a pipeline that will give us the confidence we can deliver what we need right out to the end of RIIO-T3.
In terms of the US elections. I mean, first of all, to say we’re looking forward to working with the new administration. As you know energy in the US, it’s important both the federal and at the state level. We’ve heard from the new administration how important it is to keep energy prices low and how important security to supply it is. From our perspective, the vast majority of our capital investment program is determined at the state level with state policymakers and state regulators. So we’re not expecting it to have a significant impact on the £60 billion that we set out in May that we’ll deliver between now and 2029. Okay. Should I go to Deepa at Bernstein next.
Deepa Venkateswaran: Thank you for taking my questions. I have now three questions. So a couple of them are on ED3 then one on ED. So on ED3 you mentioned you want the ROE to be at the upper end of the range. Do you have any expectations on how much operational incentives the package needs to deliver? The reason I’m asking is clearly on the ASTI you want to limit your downside. So presumably the upside on Totex might be lower. So if you could just characterize how you think beyond the allowed return where else you might be able to get some extra returns? The second question is on the nominal debt allowance in ED3 that really helps from a cash flow perspective. How does National Grid — how is National Grid thinking about fast money versus slow money in the business plan?
Any sort of early hints on that would be helpful. And the last one is a clarification on ED. I think you’ve generally talked about 100 bps to 125 bps of operational outperformance in that business. But I see your latest regulatory financial performance reporting you forecasted 70 bps for ED2. So I was just wondering what’s the divergence presumably given you’re seeing the synergies et cetera are on track? Thank you.
John Pettigrew: Okay. Thanks, Deepa. I’ll take the first and then I’ll ask Andy to cover the second two. I mean first of all in terms of ROE as we said in May we were pleased to see as part of the sector-specific methodology decision document that Ofgem had recognized, the importance of the regulatory framework being one that is attractive to investors. And in the words that they used within the document itself the range that they set out which is 4.6 to 6.4. They talked about the fact that there are reasons where it potentially could be at the top end of that range. And obviously one of our focal points going forward is to have that conversation and dialogue with Ofgem about why that’s so important. Outside of the rate of return in terms of the incentives, we think and going to continue to have dialogue with Ofgem on that there are a number of incentives Deepa that would be beneficial to consumers and would be obviously if we perform well beneficial to National Grid shareholders as well which is in areas like delivering projects early.
So obviously with the size and scale of the capital program we’ve got clearly being incentivized to deliver those projects as early as possible makes a lot of sense and we’ll create value for customers. And secondly things like constraint management. So as you’ve seen over the last few years the cost of balancing system has increased. There are potentially actions that we can take as a constructive maintainer of the assets that potentially could reduce those constrained costs. So we think there’s an opportunity for incentives in those areas as well. So those are the types of things that we’re discussing with Ofgem at the moment. Andy?
Andy Agg: Yes. Thanks. So on the ED3 or the ED2 question around the 100 to 125. Yes I think we would always anticipate some differences between our overall forecast for the five years of the rate case or the price control versus what’s reported on an annual basis within the RRP. There’s several reasons for that. There are some differences between within RoRE and how it’s calculated. But also as we think about our efficiency plans and how we look to deliver that over the life we would see — record those improvements through the reported return as we crystallize those efficiencies in the outer year. So not all of it will be in the early years of the RRP. And as I said we’ll get report as we move through the outer years.
Deepa Venkateswaran : So the cost for [indiscernible] in your RRP wasn’t the last year?
Andy Agg : No, to that point as well. Apologies. Yes. So as you said the SSMD was very clear from Ofgem that they’ve chosen that particular approach in terms of the cost of debt allowance going forward. I think in terms of your broader point there around fast versus slow, I think if you take a step back, we’ve always said that we are focused on both the return the allowed return coming out in T3, but also the overall cash characteristics. I think nominal debt is a good step in the right direction in terms of it will accelerate cash. But I think we will continue to work with Ofgem to make the case that the — whether it’s through changes in asset lives the fast slow mix they are all different elements. As you know in T2, we were around 15%. So a natural rate may be somewhat lower than that, but it would always be something that we’d be looking to have as part of the overall package that we work through with Ofgem.
John Pettigrew : I’ll go to Dominic next and then after Dominic I’ll go to Jenny from Citi. Dominic from Barclays.
Dominic Nash : Hi, there. Good morning and thanks for your presentation. Just a couple of questions from me kind of following on from earlier ones I guess. Firstly, on your earnings expectation of the 6% to 8% out in your business plan. I mean, clearly you’re using the exchange rate and CPIH that may or may not be looking a little bit on the high end. But coming back to the ED3 review, how much wiggle room do you have to manage your own earnings going forward in light of a nominal return on debt and then your capitalization ratios sort of moving from the natural rates? And how will you be looking at putting that thing through in order to sort of manage your earnings? And subsequent on that one there do you expect ED3 to also have a nominal cost of debt?
My second question is on the U.S. election. Could you just remind me again how much of your capital spend in the U.S. is from imported goods? And what impact and what mitigation strategies could you put in case if there was a material increase in import tariffs? Thanks.
John Pettigrew : Okay. Well, why don’t I let Andy take the first and I’ll take the second. I’ll do the second first Andy. I mean, in terms of the — our CapEx in the U.S. to most Dominic the vast majority of it is sourced domestically. So, historically, when I look back a relatively small proportion of it has been imported on things like steel, but the vast majority of the equipment comes from domestic equipment manufacturers like GE. So it doesn’t impact us hugely if there are any changes to trade tariffs. Andy?
Andy Agg : Yes. Thanks Dominic for the questions. I think in terms of the overall impact of T3 on earnings if you go back to what we said in May, when we set out the 6% to 8% I think we were clear that we’ve made what we believe to be sensible and prudent assumptions across the five years. And obviously that would have taken into account what we expected in terms of some of the initial steps that we were seeing through the SSMC the consultation at that point. So the question specifically at nominal debt doesn’t — you shouldn’t automatically assume that that will be additive. I think as always what will be important with the T3 plan going back to the points John made around the scale of CapEx in there is that we will be looking for an overall outcome that delivers what Ofgem has said around being both financeable and importantly investable and that will, of course, include the right cash characteristics whether that comes through the normal debt impact or other things like fast slow or capitalization rate.
So we will continue to work on that. But as much from a ensuring it’s the right framework in terms of the impact on earnings. And then secondly on your question around will nominal debt flow through to ED3. Actually I think it’s been implemented now that approach by Ofgem for the sector as a whole. So I see no reason why it shouldn’t read across into ED3.
John Pettigrew : I’ll go to Jenny. And then after Jenny I’ll go to Mark Freshney at UBS. So Jenny.
Jenny Ping: Hi, thanks very much. A couple of questions from me please. Firstly to John, can you just put it into numbers in terms of that Tier 1 supply chain, what it means in terms of the total CapEx that’s covered for the 17 ASTI projects? And then, secondly, for Andy two questions please. On the U.S., if I remember correctly your guidance — your earnings guidance is based on a pre-deferred tax for the U.K. but not for the U.S. Can you just talk a little bit about what you think a change — a reduction in U.S. tax rate, would do to the deferred tax line and therefore your earnings line on a hypothetical basis? If I remember correctly, we had this conversation at Trump 1.0, but if you can just remind us the direction of travel there.
And then secondly just on the ESO, obviously there’s a lot of cash that’s already recognized because of timing. So can you give us a sense of the actual cash that you’re going to receive at the closing of the ESO, just so that we can get our net debt numbers, right? Thank you.
John Pettigrew: Okay. Thanks Jenny. Well, let me pickup the first and then leave this two and three to Andy. Let me sort of give a broader sort of perspective in terms of where we are in the supply chain, because I know it’s a key issue. So I think hopefully people are aware that over the last 18 months or so we’ve fundamentally reviewed the way that we engage and contract and procure with the supply chain. So we’ve made really good progress. So we’ve talked in the past about how we ensure that we’ve got the contractors we need in terms of the work resource. And I was really pleased that we put in place what we call the Great Grid Partnership with seven of our supply chain which is a GBP 9 billion home contract that gives them the visibility to the work that we want them to do and gives us access to that work gives us confidence that we’ll have the contractors that we need.
We’ve also been progressing the as I mentioned in my speech the HVDC and converter station framework agreement which is a GBP 59 billion contract. And actually I’ve been really pleased with the response that we’ve had all the major cable manufacturers and converter station manufacturers have responded to that framework agreement and we’re hopeful that will be in place very, very soon. And then when you get down into the individual projects we’ve separated ASTI into the first wave of six projects, five of them we have contracts in place already and are already in the process of starting construction. And the sixth which is The Grain to Tilbury project we will have planning in place by the end of the calendar year and the contracts in place by the end of the fiscal year.
So for that first wave, we feel very confident that we’ve got the contractors and the equipment that we need. We’re then moving on to the second wave. So these are projects like EGL 3 and 4 Norwich to Tilbury, those types of projects. And again, we’re working through the procurement process. We’re looking at opportunities to standardize equipment so that we have more access to the supply chain. We’re actually extending the length of contracts that we have. So across the group actually more than 50% of all the [indiscernible] transformer that we need have already been procured out to 2030 puts us in a very strong position. We’ll also have agreement with Ofgem that we can actually make upfront payments to the supply chain to lock in capacity that we need for manufacturing.
So again, when we look across all of that we feel confident for the Tier 1 contractors that we’ll have everything we need in place early next year for all of the 17 ASTI projects. So Andy?
Andy Agg: Yeah. Thanks Jenny. Firstly on U.S. and potential tax changes, I mean clearly it’s very early days and there’s been lots of things talked about or muted that may happen. We will of course have to wait and see precisely what does or doesn’t happen in the New Year. But as a quick reminder, as you said, when the rate was changed a few years ago it’s effectively economically neutral for us because the way U.S. regulation works is effectively tax, the net tax charge is included with the amounts we’re allowed to collect from customers and therefore a change in the rate will effectively flow through into rates as well. So net-net there’s no underlying earnings impact. And of course, in terms of cash impacts that will need to be worked through based on what we see if any rules do change and then how that’s reflected in regulation.
But we wouldn’t expect any significant earnings impact from that. And in terms of the system operator sale, the actual cash received was very close to the 630. If you look back in the depths of the results statement this morning, we’re very clear that the provision for the remaining return of the over collected recoveries from the previous year is included in the held-for-sale business as is the cash that was associated with giving that money back. So that was already stripped out of our numbers. And therefore, we did receive very close to the 630 and therefore that’s what you should allow for in your net debt projections.
John Pettigrew: Thanks. Should we go to Mark Freshney? And after Mark we’ll go to Robert, Morgan Stanley. So, Mark can we have your question please?
Mark Freshney: Thanks for taking my question. So, when I listen to your response to earlier questions the potential change in Ofgem remuneration of debt costs moving to a nominal cost potential lower deferred tax charge in the U.S. less netting that off on the asset base which was in response to the last question. It seems to me that if I add up all of these things within the five-year frame, there’s certainly a lot of upside pressure on earnings. And my question to you is would you agree with that? And just secondly, you spoke about being in a strong position on transformers which I think is one major, major crunch point. But if I had to really try to pin you down John, I mean we know that one customer has basically taken up all of one supergrid transformers for two years and has caused a lot of panic with some of your competitors in the U.S. In one word, are you confident of getting all the transformers you expect to get through to 2030?
John Pettigrew: Thanks Mark. Let me take the second and then I’ll ask Andy to take the first. I mean the simple answer is Mark that we’ve always known or we’ve known for a couple of years now that there was going to be an elongation in the lead-time for supergrid transformers. You would have seen some articles this week that people talked about three to four years. But we’ve been adjusting for that for quite a while now. And therefore we do have confidence that we can gain access to the supergrid transformers both in the U.K. and in the U.S. that we need over the period. As I said we’ve been extending the timeframes that we’re sharing with the equipment manufacturers so they’ve got visibility of what’s needed. And when we come to the procurement process we found that actually we have been able to get access to and to procure those supergrid transformers.
Let me just to add a little bit more flavor to it. One of the things we have done in the last 12 months is built up a stronger relationship with the equipment manufacturers outside of the sort of normal contracting process and separating out quite often the procurement of equipment from the EPC contracts. And in the U.S. we’ve also been extending the supplier base for transformers and bring us new manufactures which we started about 18 months ago. So, we remain confident that we are able to access the equipment, albeit, we didn’t recognize the lead-times are longer, but we’re reflecting in our planning processes.
Andy Agg: Yes. Thanks Mark. I mean to try and pull together sort of the elements of your question. I think again go back to when we set out the 6% to 8% guidance for our five-year earnings CAGR back in May. Of course it was deliberately designed to be robust to a range of different outcomes. And nothing that we’ve seen since then has moved us outside that range. So it remains our very clear guidance today. As I said in answer to one of the earlier questions of course we made sensible assumptions around regulatory outcomes based on what we knew at the time. And so you shouldn’t assume that things like nominal debt are automatically additive. And as I said in answer to the earlier question on U.S. tax over time, we would expect that broadly to be neutral from an underlying earnings perspective with albeit sort of one-off changes in deferred tax flowing through earlier.
So no I think we’re very clear that the 6% to 8% remains our guidance today. And we will of course if it does change we will update that down the track but that’s very clear in terms of where we stand today.
John Pettigrew: Okay. Thanks Andy. So let’s go to Rob at Morgan Stanley. And after Rob will do Ahmed at Jefferies. So, Rob can we take your question?
Rob Pulleyn: Thanks. Good morning everyone. Just one question and following up on the theme of supply chain. Way back at full year results though when we sat around the table you indicated there was a £59 billion framework agreement for the supply chain on which HVDC was the topic of the moment. Correct me if I’m wrong but I don’t think we’ve seen an update on that. Is that still expected to be closed in terms of signing before the end of calendar 2024? And could you give a bit of a comment around the HVDC side given you’ve already covered the transformers? Thank you.
John Pettigrew: Yes. Thanks Rob. So I did mention it in the speech but just giving you a bit more flavor on it. So we launched the procurement process for the Framework agreement early this year. As I said, it was a major Framework agreement that will cover not just the CapEx that we need and the supply of HVDC cables between now and 2029 but actually take us well into the 30s as well. We’ve been really pleased with the response that we’ve had from all the major cable manufacturers in the world. And we are hopeful that that framework agreement will be in place either by the end of the calendar but certainly. by the end of the fiscal year. So we’ve had really good progress and a very strong response and we feel very confident about it.
In terms of — just again, just going down a level. So in terms of the first wave of ASTI projects, the contracts are in place for giga 1 and 2, which are the major HVDC contracts that we needed as part of Wave 1. So again, we’re in good shape on that. Those contracts have already been let. As I said earlier, we’re already in the construction phase on those. Okay. I’m going to go to Ahmed at Jefferies, and then I’ll go to Marcin at Bank of America.
Ahmed Farman: Yes. Thank you for taking my questions. Can I just kind of go back to ED3? You clearly discussed and given us quite a lot of color on your confidence and visibility that you have and talked a lot about supply chain and procurement. Could you also give us some perspective on the consenting and planning visibility do you have on ED3 and put some numbers around it, is there sort of a Phase 1 does that already all consented and you have all the approvals in place to deliver that? That would be helpful. And maybe tie it into that the spatial energy plan, how critical that is to the delivery of the plan? And what do you need to see and the timing of that that would be super helpful. And just finally I’ll be interested in your perspective on 2030 Clean Power Plan. Anything particularly notable within that, how does that compare to your CapEx plan that you set out to us earlier in the year? Thank you.
John Pettigrew: Okay. So, quite a bit Ahmed. Let me work through with that. So in terms of planning, I mean first of all, as you know we’ve been advocating for planning reform for some time. And we’ve seen that issue being picked up by the new labor government. And our expectation is that there will be planning reform legislated for next year. National Grid has been advocating for a number of things within that. One is the streamlining of the process consistent really with what the Networks Commissioner, Nick Winser, recommended about a year ago. We’ve also been recommending that there should be an accelerated planning process for strategically — strategic important infrastructure such as transmission and we’ve been advocating for that.
But also, talking to the government about the need for resourcing planning authorities because there’s such a massive increase in the amount of planning applications that resourcing is important as well. But we’re hopeful that we’ll see sort of positive progress in that through the legislation next year. In terms of where we are on our specific projects, as I said we’ve made excellent progress on the Phase 1 project at ASTI all in line with the time scales that we need to deliver these projects. So we’ve had DCO applications approved by the sector state for Bramford to Twinstead and Yorkshire Green. And we’ve had planning consents for filing of the for all of the other Phase 1 projects with the exception of Grain to Tilbury. which is due for planning consent at the end of this calendar year.
So, good progress on that. Over the summer, I think we’ve had eight separate consultations running in preparation for Phase 2. Again they’re all at different stages. Some are at the pre statutory consultation phase, Norwich to Tilbury, which is one of the major projects in Phase 2. We’ve just completed the statutory consultation on. So again, they’re all moving through the process. These are multiyear projects and therefore, we only go to the planning authorities at the right time. And we do a huge amount of consultation with local communities to make sure they understand the options in what we call the pre-statutory consultation phase to make sure we understand the community’s concerns and we can try and reflect that in our recommendations to the secretary state as well.
In terms of the spatial energy plan. It’s probably useful just to sort of link the three — the sort of the different elements together. So, obviously, foundational block has been what’s been announced this week by the National Energy System Operator, which is the Clean Power Plan for 2030. Obviously, that advice will now feed into government who are proposing that they’ll come forward with what their action plan is at the end of this year. You may have seen a couple of weeks ago that the government also commissioned NESO to do the spatial energy plan and that is due to be complete by the end of 2026. And on the back of that we’ll then see the centralized strategic network plan in 2027. So all of these things sort of interconnect, but the foundation block, I guess is the Clean Power Plan, what comes back from government at the end of this calendar year.
From our perspective, obviously, we’re working through the detail of it. As NESO said, it’s a hugely ambitious plan. I think the words they use it at the limits of what is feasible and it will require everybody to play their part and for everybody to play their parts in executing it and doing it flawlessly. From our perspective looking at the networks reassuringly, what the plan says is the projects that were identified previously the 17 ASTI projects are the ones that are going to be required for Clean Power 2030. There is a recommendation in that report that two of the projects which is Nowrich to Tilbury and Sea Link. There’s a request on whether they can be brought forward by one year from 2031 to 2030? Obviously, we’ll spend some time now working both with our supply chain, but also with government regulator NESO.
And what would be required and whether that’s possible. And obviously that will feed in ultimately to the action plan that the government produces at the end of this calendar year. Okay. I’m going to go to Marcin next and then I’ll go to Ingo at Kepler. So Marcin?
Marcin Wojtal: Thanks so much. Good morning. Two questions here. Firstly on the rate case for Massachusetts Electric how satisfied you are with the outcome of 9.35%? I believe you were actually requesting something closer to 10%. And how confident you are that you will actually achieve a return which is very close to the allowed return in that business? And my second question relates to potential asset divestments of US renewables and LNG grain. I believe both of these have been now reclassified to assets held for sale. So from the accounting perspective does it imply that you are confident that both of these assets will be sold within the next 12 months? Thank you.
John Pettigrew: Okay. Well I’ll pick up the first and I’ll ask Andy just to pick up the second. In terms of the Massachusetts rate case, I mean, it was a landmark rate case I think in my mind because the key elements, which are really important, to focus in on is that what we got an agreement from the regulator in Massachusetts is that, there can be a revenue adjustment for increasing capital investment. As you know, we’ve got significant capital investment in our Massachusetts business and the regulator effectively agreed that our revenues could increase year-on-year as our CapEx increases. At the same time, they also confirmed the performance-based mechanism for indexation of revenues for operational and maintenance costs.
So when you put that together Massachusetts, as a rate case now looks a lot more similar to what we had in New York. And whereas in the past Massachusetts has always had higher allowed returns than New York. It’s always been on a historical base case for costs. And therefore, it’s always been harder to earn those allowed returns. I think the new framework that we have in place makes it much more akin to the framework we are familiar with in New York. And therefore, we are much more confident that we can achieve much closer to allowed return. And as you know, our objective in the US businesses is always to aim for at least 95% of allowed returns. So we’re much more confident around that than we were in the previous region.
Andy Agg: Yes, and thanks so on the divestments I think as John said earlier the first one is the National Grid Renewables business in the US, where that process is underway. And yes so we expect that, to press through into the beginning or the early part of next year. And then as we said, previously, on the Grain LNG sale, we would expect that process to commence when we’re through the completion of the construction of the current Phase 4, the new tank which is expected around the end of the first quarter of next year. So yes to your precise question on the accounting our judgment is that we would expect both to be complete within 12 months from the 30th of September.
John Pettigrew: Thanks, Andy. Ingo, I think this is the last question. So if we can have your question please.
Ingo Becker: Yes. Good morning. I hope you didn’t answer them already I had a brief connection issue. First, I would like to ask you on the data center comments in your slides. So you say that in the UK. Southeast the transmission scale data center connection request. Can you comment on how many 12 months that is and if that creates any relevant impact on the local system balance in your assessment? And my second question would be on the general affordability of the expanding network cycle, maybe both in the UK and the US. We have heard in some markets of rising supplier equipment prices which probably is not a surprise, given the rising demand from the network companies coming to the attention of regulators. Just wondering, if you can share similar experiences here?
And finally maybe related to the German conservative party and the current situation has been talking about actually cutting grid fees quite materially it’s not yet totally clear what they mean. We suspect that it’s about transferring some of the network cost to the government budgets, but we don’t really expect them to go at the returns. And maybe if you hear as well just from an overall affordability perspective what that cycle will do to you? Thank you.
John Pettigrew: Thanks for the question. I mean let me just paint a picture in terms of data centers. I think it’s an evolving picture and therefore one that we’re spending quite a bit of time focusing in at the moment. At the macro level, when you look forward over the next decade, we are certainly going to see increasing load growth on the networks both in the US and the UK. We’ve known that’s coming because of electrification of transport and electrification of heat. But actually the volumes of electricity being consumed in terms of Generative AI and AI is an additive factor to that and we’re just continuing to understand what that’s going to look like. What we see today if I take the UK as an example is around about five terawatt hours of the load in the UK is taken by data centers.
That represents about 1.8% of the total load in the UK. If you actually look at what’s been happening over the last three years historically the data centers in the UK are sort of clustered around the M25 and the sort of [indiscernible] corridor. We’ve got the good sort of telecom networks. We had about 1.5 gigawatts there three years ago and we’ve seen about three gigawatts of connection applications on top of that. So it’s a tripling of the size of data centers that we’ve seen in that region. And the vast majority have been in that region. And as a result we’ve — we continue to invest in particularly expanding the substations and new substations in that area. More recently we are seeing more interest for the sort of hyperscalers so much larger data centers in other parts of the country including the Northwest.
And if you look at the connections queue, there are about 10 gigawatts in terms of data center demand that’s saying they potentially want to connect to the grid over the next sort of 15 years. As we know that doesn’t always happen but that’s an indication of the sort of scale of what we’re seeing. And some of these data centers are getting to be very large sort of 200 megawatts type size. And just to put that into context 200 megawatts is larger than the load for households for every city in the country apart from Manchester, Birmingham and London. So when these data centers want to connect it is a significant increase in load. And the final point I’ll probably make is that, when you see the business plan that we’re submitting to Ofgem as part of RIIO-T3, you will see actually that probably the largest driver in terms of additional transformers over the five years of RIIO-T3 is actually being driven by data center demand as well in the UK.
Picture in the US is slightly different because about 90% of all data centers are currently not in the Northeast. Generated land prices and energy prices are lower than the Northeast. Although we are starting to see increasing interest in New York. We’ve got about 1.5 gigawatts of potential data center demand about one-third of that’s in our territory. Massachusetts is a little bit less. I think we’ve got three live connections at the moment the largest of which is a [indiscernible] data center demand request. So it’s an evolving picture and one that we’re very much focusing on at the moment. And as I said in T3, you’ll see some of the load increases and some of the transformer investment we’re doing has been driven by that. In terms of affordability, it’s always worth just reminding people that if I start in the UK, the transmission element of the bill is a relatively modest part.
That doesn’t mean we don’t focus on driving efficiency for our customers. But today transmission represents about £20 of the total annual bill that consumers pay around £1700 a year. So even with our £60 billion capital investment program which will increase the cost of infrastructure by a few pounds ultimately if you believe that it will have the benefit of reducing the commodity element of the bill then the affordability of customers should be manageable. The Clean Power Plan for 2030 that NESO just issued has got some detailed analysis on what costs might look like. We’re currently having a look at that as well. In the US slightly different because we are the supplier as well as the network provider. We work very closely with our regulators when we do rate filings.
You would have seen in the more recent rate cases that we’ve got significant increases in capital investment. And one of the ways we mitigate the affordability issues is by proposing programs to help vulnerable customers. And that’s something that our regulators are really appreciating from National Grid when we work through different programs to reduce the cost for vulnerable customers during periods when affordability is an issue.
John Pettigrew: Okay. In which guys I’m going to say I don’t see any other questions. So I’m going to say thank you everybody for joining us this morning. And I think my key messages really are good performance right across our regulated businesses in the first six months good progress in terms of the strategic priorities that we set out in May and a strong start to the delivery of our £60 billion capital program also we set out in May. So thank you for joining us and I’ll see you all very soon.